30 ÷ 5 = 6
6 obreros quitan 1 dia
40 ÷ 6 = 6,66
Redondeamos a 6,70
= 6 dias 7 horas aprox.
40 obreros se demoraran 6 dias, 7 horas para cavar una zanja
Respuesta:
☝️☝️☝️☝️☝️☝️☝️☝️☝️☝️☝️☝️☝️