Verified answer
A = 32 hr; b = 25 org; c = 20 hr; d = ? orga . b = c . d
32 . 25 = 20 . x
800 = 20x
800/20 = x
x = 40
Jadi, tambahan pekerja yang diperlukan adalah...
40 - 25
= 15 org
Semoga membantu (*w*)
Verified answer
32 hari ---- 25 orang20 hari----- X orang
X = (32.25) ÷ 20
X= 800 ÷ 20
X = 40 orang..
tamaban pekerja
40 orang - 25 orang = 15 orang
maaf kalau salah ya...